Markolines Pavement Technologies has picked up three orders worth Rs 234.83 crore including GST, and the biggest is a bridge, not a road surface. A Rs 120.28 crore sub-contract covers the balance works of the major bridge over Middle Strait Creek on NH-4 in the Andaman Islands. It comes two weeks after the company’s Rs 135.20 crore BMC microsurfacing orders in Mumbai, and it pushes a pavement-maintenance specialist onto a concrete job on an island where every machine has to arrive by ship.
The work at a glance
- Middle Strait Creek bridge, NH-4, Km 106.590 to Km 108.553, linking South Andaman and Baratang Island: Rs 120.28 crore, 18 months, work order from RKEC Projects.
- NH-4 rehabilitation and upgradation, Km 155 to Km 181 (end of Jarwa to Rangat): Rs 57.84 crore, 6 months, also from RKEC Projects.
- Major maintenance with a complete overlay, Km 634 to Km 681 in Andhra Pradesh: Rs 56.71 crore, 180 days, from Ranastalam Anandapuram Road Limited.
- All values include GST. The three add up exactly to the Rs 234.83 crore total.
What Markolines disclosed
The details come from the company’s Regulation 30 filing on 16 November, signed by chairman and managing director Sanjay Patil. A corrigendum filed later the same day says the two RKEC documents are work orders, not letters of award, and changes nothing else. Both Andaman jobs are sub-contracts: RKEC holds the main contracts, and the bridge is an NHIDCL project. EquityBulls carried the same three values, clients and chainages the same morning.
Which machines this work needs
The bridge is the heavy one. The chainage runs 1.963 km, which covers the creek crossing and its approaches, and the money works out to about Rs 6.7 crore a month over 18 months. The filing does not list which parts of the structure are still to be built, so the fleet depends on that. Balance work on a creek bridge usually means a crawler or mobile crane for girders and reinforcement, a site batching plant, a concrete pump and transit mixers, and possibly piling equipment if foundations remain. On an island, the contractor has to ship most of this in, which favours owned plant that stays for the full term.
The 26 km NH-4 stretch is a different kind of job. At roughly Rs 2.2 crore a km including tax, inside six months, it is rehabilitation on an existing road. It pulls a motor grader, soil and tandem compactors, an asphalt paver, a hot-mix plant and tippers. Six months is tight for an island site, so expect plant to be mobilised once and shared between the bridge approaches and the road.
The Andhra order is plain resurfacing. Rs 56.71 crore over 47 km is about Rs 1.2 crore a km including GST, which sits in the overlay band with no earthwork. The filing gives chainage, not lane-km or layer thickness, so the asphalt tonnage cannot be sized from it. The kit is a paver, tandem and pneumatic rollers, tippers and a nearby hot-mix plant, and 180 days is short enough that hire is the likely route for rollers and tippers.
Quoting for bridge or highway work? Compare road construction equipment, check current crane and paver models, and talk to dealers before you commit to shipping plant to a remote site.
What follows next
- Start dates on the two Andaman jobs, and whether the six-month road clock begins before the bridge mobilises.
- Any update from NHIDCL on the Middle Strait bridge completion date now that a sub-contractor is in place.
- Further sub-letting by RKEC on NH-4, which would show how much of the island work is being passed down.
FAQ
Is Markolines the main contractor on the Middle Strait bridge?
No. Its filing describes the order as sub-contracting work from RKEC Projects. The project itself is listed by NHIDCL as the balance works of the major bridge over Middle Strait Creek on NH-4.
Do the order values include tax?
Yes. The filing states each value including applicable GST: Rs 120.28 crore, Rs 57.84 crore and Rs 56.71 crore.
How long will the work take?
The filing gives 18 months for the bridge, 6 months for the NH-4 road stretch and 180 days, including mobilisation, for the Andhra overlay.