Ashoka Buildcon now holds two back-to-back stretches of the Vadodara-Mumbai Expressway in south Gujarat. On 20 November it told the exchanges it has NHAI’s Letter of Acceptance for Package VIII, the Jujuwa-Gandeva section, at Rs 1,465 crore before GST. Eleven days earlier it took the Rs 866 crore Package IX next door. One contractor now has about 62 km of unfinished eight-lane expressway, with the same 18-month clock on both packages.
Key numbers
- Client and stage: National Highways Authority of India, Letter of Acceptance disclosed on 20 November 2026. Ashoka was declared lowest bidder on 17 November.
- Scope: balance work on the eight-lane, access-controlled Jujuwa-Gandeva section, Km 154.6 to Km 190 (35.4 km), Package VIII, Gujarat.
- Value and mode: Rs 1,465.00 crore excluding GST, on an EPC contract.
- Term: 18 months to complete, then a 10-year defect liability period.
What the filing and the record show
The scope, value and terms come from Ashoka’s Regulation 30 filing, which we read in full. Construction World and Arthneeti carried the lowest-bid stage on 17 November with the same value and section. The filing calls the job “balance work”, but little of the stretch was built. A Lok Sabha reply reported by DeshGujarat in August put Package VIII at 4.85% physical progress, with the earlier contract terminated for poor performance, and NHAI had to re-tender what was left.
Does a stretch that is 95% unbuilt change what contractors should line up?
It does. Rs 1,465 crore over 35.4 km is about Rs 41.4 crore per km. Package IX works out to about Rs 32.6 crore per km, and the same Lok Sabha reply put that stretch at 21.75% done. The emptier stretch costs more per km because more of everything is left: formation, structures and pavement.
So treat Package VIII as close to a full build. Embankment work needs excavators loading tipper fleets, with dozers spreading fill. Every layer then needs soil compactors to pass density tests, and motor graders to trim the subgrade, sub-base and WMM before the paving train arrives. On an access-controlled road each crossing becomes an underpass or overpass, so batching plants, transit mixers and cranes will be on site too. The filing gives no structure count, so nobody can size that concrete work yet. Our road construction equipment guide lists which machine does which layer.
The calendar matters more than the value. South Gujarat earthwork largely stops from June to September, so 18 months gives roughly two dry seasons of real output. Both packages share that window. If Ashoka runs them as one site, expect shared batching and paving plant, and heavier short-term hire of rollers, graders and tippers across Valsad and Navsari districts in the dry months. Hire owners in the region should price for a peak, not a steady 18-month booking.
Dates to note
- The appointed date for Package VIII. The 18-month term runs from it, not from the LoA.
- The June to September 2027 monsoon, which falls inside both packages’ windows.
- Separately, Ashoka’s joint venture with SAM India was declared lowest bidder on 20 November for Jaipur Metro Phase II Packages 3 and 4 (elevated viaduct with 12 and 11 stations, Rs 2,758.31 crore including GST). That is a bid result, not an award yet.
FAQ
Is the Jujuwa-Gandeva stretch new work?
The filing calls it balance work, but an August Lok Sabha reply put the package at 4.85% progress. Nearly all of it is still to be built.
How does it connect to Package IX?
Package IX runs from Km 128.0 to Km 154.6 (Karvad-Jujuwa). Package VIII starts at Km 154.6 and runs to Km 190. Ashoka holds both, about 62 km, worth Rs 2,330.90 crore together before GST.
When will machines be needed?
Once NHAI issues the appointed date. The 18-month term then spans two dry seasons and one monsoon.
Bidding for hire work on a Gujarat expressway? Compare motor graders and compactors on DesiMachines, with specs and running costs, before you quote a monthly rate.
Related on DesiMachines: Morbi six-lane highway: Rs 1,182 crore sanctioned for the NH-151A port link
Newer: PUC Rules November 2026: Two-Year Test for Young BS-VI Tippers, Six Months for BS-IV
Source: Ashoka Buildcon Regulation 30 filing (BSE)