Pirpainti Transmission Project: Adani Energy Wins 881 ckm Bihar Scheme

By 4 min read
Pirpainti Transmission Project: Adani Energy Wins 881 ckm Bihar Scheme

Adani Energy Solutions (AESL) has won the Pirpainti transmission project in Bihar, the network that will carry power out of the 2,400 MW thermal plant Adani Power is building at Pirpainti in Bhagalpur district. The Bihar cabinet approved AESL’s selection as the successful bidder on 18 November and the company announced the win a day later. For contractors with excavators, piling rigs and cranes, this is roughly 881 circuit km of new line and four substations to be built across north and central Bihar by the end of 2028.

The work at a glance

  • 881 circuit km (ckm) of transmission line and 3,160 MVA of transformation capacity, company-stated.
  • Four gas-insulated substations (GIS) at Jhanjharpur, Bethauli and Begusarai, plus 400 kV line bays at the Bakhtiyarpur grid substation.
  • 400 kV double-circuit lines Pirpainti-Jhanjharpur, Pirpainti-Begusarai and Begusarai-Bakhtiyarpur; 220 kV double-circuit lines Jhanjharpur-Bethauli and Begusarai-Begusarai Town.
  • Annual transmission charge of Rs 493 crore for 35 years, paid by the two state discoms, after which the assets pass free to Bihar State Power Transmission Company. Completion is targeted for the fourth quarter of 2028.

What was decided

The scheme, titled “Evacuation of Power from 3X800 MW STPP Pirpainti”, was bid under tariff-based competitive bidding. Indian Masterminds reported the cabinet decision on 18 November, including the Rs 493 crore tariff and the 35-year term. BusinessLine and Free Press Journal carried the company’s release on 19 November, which puts the tariff at about Rs 500 crore and names Vikramshila Power Transmission Ltd as the project company. No construction cost was disclosed. The Rs 91,500 crore figure in the headlines is AESL’s whole transmission capex pipeline, not this job.

Which machines this work needs

Start with the lines, because that is where most of the machine hours sit. Every named line is double-circuit, so 881 ckm works out to something near 440 km of route. On typical spans of 350-400 m that is more than a thousand tower locations, each with four foundation pits. That is excavator and backhoe loader work in short bursts, with a transit mixer feeding each footing and a crew moving on within days. It suits hire, not purchase, for most subcontractors.

Geography changes the foundation mix. Both 400 kV lines from Pirpainti end at towns north of the Ganga, and the Begusarai-Bakhtiyarpur line runs back south, so the routes as named need river crossings. Crossing towers and towers on soft, flood-prone ground in north Bihar usually sit on piles or well foundations, which brings in piling rigs and larger cranes. Those packages are fewer, heavier and longer-running than the ordinary tower pits.

The substations are a smaller earthwork job than the line count suggests. GIS halls take a fraction of the land an open-air yard needs, so platform grading is modest. The spend goes into concrete buildings, transformer plinths and crane lifts for 400 kV equipment.

One caution on timing. AESL is the concession holder, not the crew in the field. Machines get hired or bought when it lets the tower, foundation and civil packages beneath it, and the north Bihar flood season limits the useful window to roughly October to June. That leaves about two dry seasons before the 2028 target. More on power-sector fleets is in our power and renewable energy guide, and state listings are on the Bihar page.

What follows next

  • Transfer of Vikramshila Power Transmission Ltd to AESL, the formal step that starts the concession clock.
  • Tower erection and foundation subcontracts, especially the Ganga crossing packages.
  • Progress on the Pirpainti power plant itself, which the line is built to serve.

FAQ

Who won the Pirpainti transmission project?

Adani Energy Solutions, selected through tariff-based competitive bidding. The Bihar cabinet approved its selection on 18 November 2026.

What is the project’s cost?

No capital cost was disclosed. The disclosed figure is the annual transmission charge of Rs 493 crore for 35 years, which the company rounds to about Rs 500 crore.

When will it be finished?

AESL targets completion in the fourth quarter of 2028.

Lining up for tower foundation work in Bihar? Compare excavators, backhoe loaders and cranes, and check finance options on DesiMachines before the subcontracts are let.

Related on DesiMachines: Adani’s Satara transmission project win in Maharashtra

Newer: Dilip Buildcon Gurugram Metro Depot: Rs 419 Crore LoA Received

Source: BusinessLine

Share this article:

Disclaimer: *All logos, trademarks, brand names, images, videos, documents, and product information displayed on DesiMachines are the property of their respective owners. DesiMachines is an independent aggregator working with OEMs, authorised dealers, channel partners, and publicly available sources. Display of any brand or content does not imply partnership or endorsement. Product details, specifications, prices, and availability are indicative and subject to change. Users should verify final details with the respective dealer or seller. DesiMachines is not liable for any inaccuracies or decisions made based on the information provided.

!

Let's get started

Disclaimer

Desi Machines is a platform where you can see and compare construction equipment. It showcases images, brochures, features, technical specifications, brand details & dealer information. All these are taken from respective brand websites, brochures, and other public resources. We do not claim ownership of these materials and strive to ensure their accuracy. However, the disparity may happen and we advise users to verify directly with respective brands and dealers. Desi Machines is not liable for any inaccuracies or reliance on the information provided. Use of this website is at your own discretion.

Read the full disclaimer

Compare