Suno Sabki, Chuno Apni.
Chat with us
Infrastructure & Projects

ARSS Infrastructure Wins Rs 131 Crore Northern Railway Bridge Order in UP

Reviewed by 4 min read
ARSS Infrastructure Wins Rs 131 Crore Northern Railway Bridge Order in UP

ARSS Infrastructure Projects has won a Rs 131.10 crore work order from Northern Railway to design and build a new rail bridge on the Jaunpur-Zafrabad doubling in Uttar Pradesh, and then take down the old one beside it. For machine owners this is a foundations, concrete and crane job at one site, with a second burst of crane work at the end when the old girders come out.

The work at a glance

  • Client: Northern Railway, Lucknow Division. Letter dated 14 November 2026, disclosed to the exchanges on 16 November.
  • Value: Rs 131.10 crore (Rs 131,10,40,131.85 in the filing). Contract form: EPC.
  • Scope: Important Bridge No. 75, 14 spans of 30.5 m composite girders, built next to the existing 16-span plate girder bridge at km 826.710 on the Jaunpur-Zafrabad section. Protection work and dismantling of the old bridge are included.
  • Time: 825 days from the Appointed Date, which has not been announced.

What ARSS disclosed

ARSS, a Bhubaneswar contractor that builds rail, road, bridge and irrigation works, reported the order after market hours on 16 November under the SEBI listing rules. The letter number, span details and completion period come from the filing as reproduced by Kalkine India. HDFC Sky, Angel One and Equitypandit each carried the same value, client and Lucknow Division location, and HDFC Sky also noted the protection work and the dismantling of the existing bridge. The filing does not say whether the value includes GST, and it does not name the foundation type.

Which machines this work needs

Start with the size. Fourteen spans of 30.5 m give about 427 m of new bridge, so the order works out to roughly Rs 31 lakh per running metre, with the protection and dismantling work folded in. Railways class a bridge as “important” mainly on the size of the waterway it spans, and the protection scope points the same way. That means foundation work in a channel bed, which normally has to be done in the dry months between the monsoons.

The foundation choice decides the first fleet, and the filing does not give it. Bored piles would bring a hydraulic piling rig and a service crane. Well foundations would bring a crawler crane with a grab for sinking the wells. Either way, a batching plant on or near the site, transit mixers from the concrete mixer range and a concrete pump will run for most of the 825 days, because piers, pier caps and the composite deck slab are all cast in place.

Composite girders are steel girders that take a concrete deck. The steel arrives in sections, so a crane of enough capacity for the girder lifts is the key hire. The old plate girder bridge sits right alongside, and lifts close to a working line usually happen in short traffic blocks. That makes the heavy crane a hire-by-the-week machine, not one a contractor buys for this single bridge.

Protection work (aprons, pitching and approach slopes) is excavator and tipper work: a 20-tonne class excavator placing stone, tippers bringing it from the quarry, and a compactor on the approach banks. Dismantling at the end needs the crane again, plus gas-cutting crews and trailers to clear the old girders.

The likely pattern: ARSS keeps its own concrete train on site for two-plus years, and local owners near Jaunpur get the shorter hires. Those are the heavy crane, the stone-placing excavators and the tippers. Similar jobs are listed under bridge and tunnel applications.

What follows next

  • The Appointed Date under the EPC agreement. The 825-day clock starts there, roughly 27 months.
  • The foundation type and any sub-contracts for piling, well sinking or girder fabrication. These will show which specialist machines are needed.
  • June to September: the monsoon usually stops work in the channel, so the first dry season after the Appointed Date matters most for foundations.

FAQ

What did ARSS Infrastructure win from Northern Railway?

A Rs 131.10 crore work order to design and build Important Bridge No. 75 on the Jaunpur-Zafrabad doubling in Lucknow Division, with protection work and dismantling of the old bridge.

How long is the new bridge?

It has 14 spans of 30.5 m each, which adds up to about 427 m. The old bridge beside it has 16 spans of 25.52 m.

When will work start?

The contract runs 825 days from the Appointed Date. That date has not been made public yet.

Own a crane, excavator or tipper fleet in eastern Uttar Pradesh? Rail bridge contractors hire heavy lifts and stone-placing machines by the week. Compare models and finance on DesiMachines before the work fronts open.

Related on DesiMachines: Markolines wins Rs 234.83 crore of bridge and road orders in Andaman and Andhra Pradesh

Source: Kalkine India

Machines, tenders and news for this industry: Railway and Metro

Share this article:

Disclaimer: *All logos, trademarks, brand names, images, videos, documents, and product information displayed on DesiMachines are the property of their respective owners. DesiMachines is an independent aggregator working with OEMs, authorised dealers, channel partners, and publicly available sources. Display of any brand or content does not imply partnership or endorsement. Product details, specifications, prices, and availability are indicative and subject to change. Users should verify final details with the respective dealer or seller. DesiMachines is not liable for any inaccuracies or decisions made based on the information provided.

!

Let's get started

Disclaimer

Desi Machines is a platform where you can see and compare construction equipment. It showcases images, brochures, features, technical specifications, brand details & dealer information. All these are taken from respective brand websites, brochures, and other public resources. We do not claim ownership of these materials and strive to ensure their accuracy. However, the disparity may happen and we advise users to verify directly with respective brands and dealers. Desi Machines is not liable for any inaccuracies or reliance on the information provided. Use of this website is at your own discretion.

Read the full disclaimer

Compare