Jyoti Structures has a fresh letter of intent worth Rs 272 crore from Sterlite Grid 5 to finish the 400 kV double-circuit Xeldom-Narendra transmission line in Goa and Karnataka, with 18 months to do it. Only Rs 175.67 crore of that is new money, and part of the total pays for work already done, so foundation sub-contractors and hire firms should size this as a restart of a stalled line, not a fresh 400 kV job.
What was announced
- Value: Rs 272 crore excluding GST, of which Rs 175.67 crore is incremental (company-stated in its exchange filing).
- Client: Sterlite Grid 5 Limited, which took over Sterlite Power Transmission’s infrastructure business under an NCLT Mumbai order of 5 September 2024.
- Scope: supply of materials and services, including civil and erection works, for the balance works and the works already executed on the line.
- Time: 18 months from the letter of intent dated 25 November 2026, which points to about May 2028.
What Jyoti Structures disclosed
The company told BSE and NSE on 26 November, in a Regulation 30 filing received at 9:21 am, that the new letter replaces terms on a contract it first disclosed on 26 September 2022. That 2022 order, from Sterlite Power Transmission, covered 400 kV and 220 kV double-circuit lines in Goa and Karnataka. Business Upturn carried the same value, split and term that morning.
The line has been waiting a long time. When Sterlite Power reported completing the 400 kV GTTPL gas-insulated substation in Goa in November 2024, the trade magazine Powerline wrote that the Xeldem-Narendra line was the last piece still to be completed. Two years on, the contract has been re-papered rather than closed.
Does this change what a line contractor or hirer should line up?
For a 400 kV line, the machine work sits in the tower foundations, not in the steel. Each tower location is a separate pit: excavate, place reinforcement and stub, pour concrete, backfill and compact, then move on. That is backhoe loader and small excavator work, with a small batching set or concrete mixers, tippers, and plate compactors for backfill. Tower erection itself is mostly manual gangs with derricks, plus a crane where access allows.
The filing does not give the line length, the number of towers left or how much of the Rs 272 crore pays for work already done. Without those, nobody can work out a per-tower rate, and we will not guess one. What is clear is the money shape: the Rs 175.67 crore increase is the most a buyer can treat as forward work, and probably less, since materials supply sits inside it too.
Our read: a scattered set of short-stay pits over 18 months is a hire pattern, not a purchase case. Low-bed moves between locations eat any margin from owning a machine against one line. Local operators in Goa and north Karnataka who already run backhoes are best placed. That is an inference, not something Jyoti has said.
The company also says its lenders now provide bank guarantees and letters of credit under its NCLT-approved resolution plan. For sub-contractors that matters more than the headline: it bears on whether mobilisation advances and running bills move on time. This follows Jyoti’s Rs 689.93 crore GETCO 765 kV order in Gujarat in October. Our power and renewable energy equipment guide lists the classes used on line and substation work.
Dates to note
- 25 November 2026: letter of intent date, which starts the 18-month clock.
- Around May 2028: completion due under the new letter.
- The Goa and Karnataka monsoon, roughly June to September, halts most open foundation work, so the next two dry seasons carry the bulk of the pits.
Pricing a backhoe loader or mixer for tower-foundation work? Compare models, specs and dealer prices on DesiMachines, and check finance options before you choose buying over hire.
FAQ
Who gave Jyoti Structures the Rs 272 crore Xeldom-Narendra order?
Sterlite Grid 5 Limited, the company that took over Sterlite Power Transmission’s infrastructure business in 2024. The letter of intent is dated 25 November 2026.
Is the full Rs 272 crore new work?
No. The filing says Rs 175.67 crore is incremental and that the letter covers both balance works and works already executed.
How long does Jyoti have to finish the line?
18 months from the letter of intent, which puts completion around May 2028.