The road transport ministry has proposed a rewrite of its Model Request for Proposal for highway EPC contracts that would tie how much a contractor can bid to its performance rating and to delays on the jobs it already holds. For anyone buying or hiring out graders, pavers and excavators to national highway contractors, that matters: it decides which firms keep winning work and how much cash they have left once their guarantees are lodged.
What the proposed rule says
- Bid capacity would depend on the contractor’s performance rating and on execution delays in ongoing projects, replacing the old test based on its best financial year.
- Performance security would range from 3 to 5 per cent of the bid price, depending on the rating.
- Joint ventures would be capped at two members instead of three, and generally allowed only on projects above Rs 1,000 crore.
- Sequential counter-offers to the second and third lowest bidders would go; if the lowest bidder is ineligible, the authority may annul and re-tender.
What the ministry announced
According to a ministry statement reported by PTI on Thursday, 26 November, the revision updates the framework issued in March 2019 and touches six RFP sections, 12 appendices and nine annexures, with three new formats. Bidders would have to disclose ongoing disputes, litigation, arbitration and penal actions and keep that information current while bidding. The list of non-performance criteria is cut from 20 to 7, with defined thresholds and look-back periods, and clauses on catastrophic failure, termination, debarment and insolvency are tightened. ET Infra’s report of the same statement adds new eligibility criteria for major bridges, structures and tunnels. The reports call it a proposal; none gives an effective date or a comment window.
Who has to act
Highway EPC contractors first. Under the proposal a firm running late on its current packages would see its bid capacity shrink, so the fastest way to keep bidding is to finish existing work. That points to more shifts and hired machines on delayed sites, not new purchases for jobs not yet won. Our bid capacity guide explains how the current formula works.
The guarantee change is plain arithmetic. On a Rs 500 crore package, 3 per cent is Rs 15 crore of security and 5 per cent is Rs 25 crore. That extra Rs 10 crore usually sits with the same bank that funds a contractor’s machine loans, so a weak rating could tighten both. See how a performance bank guarantee eats into working capital.
Smaller contractors are the other group. Many entered large packages as a third JV partner. With two members at most, and JVs mainly above Rs 1,000 crore, more of them would bid alone on smaller works or work as sub-contractors. For owners of motor graders, rollers and pavers, that means more hire work through big contractors and fewer small firms holding NH contracts directly. The road construction equipment guide lists the fleet these jobs use.
One more effect: dropping counter-offers means a failed lowest bid leads to a fresh tender rather than an offer to the next bidder, which could push some awards, and the start of work, back by months.
FAQ
Has the new model RFP for highway EPC contracts taken effect?
No. The ministry described it as a proposed revision on 26 November. The reports give no date from which it would apply.
How will bid capacity change under the proposal?
It would be linked to the contractor’s performance rating and to delays on ongoing projects, with existing commitments weighted by those delays, instead of using the best-performing financial year.
How many partners can a highway JV have under the proposal?
Two, down from three. JVs would generally be permitted only for projects above Rs 1,000 crore.
Deadlines and thresholds
- Rs 1,000 crore: the project size above which JVs would generally be allowed.
- 3 to 5 per cent: the rating-linked performance security band.
- 7 non-performance criteria, down from 20.
- Effective date: not announced. Watch for the final notification.
Planning a grader or roller purchase around NH work? Check equipment finance options before your bank limits are tied up in guarantees.
Related on DesiMachines: Catastrophic Failure Clause: Ministry Moves Against Two Highway Developers
Source: The Week (PTI)