The Cabinet Committee on Economic Affairs on 25 November approved a second container terminal at Kamarajar Port, north of Chennai, at an estimated Rs 4,288.26 crore including GST. A private concessionaire will build and finance it on a design, build, finance, operate and transfer (DBFOT) basis, and nobody has been selected yet. For contractors and plant owners in Tamil Nadu the work is real but some way off. It is a piling, concrete and yard-compaction job, and the bidding has to happen first.
What was announced
- A 900 m terminal with an 18 m design draft and 2.0 million TEUs a year of capacity, able to take ships of up to 24,346 TEUs and 400 m length.
- Phase I: 1.1 million TEUs for Rs 2,429.32 crore. Phase II: 0.9 million TEUs for Rs 1,858.94 crore.
- 40-year concession including 48 months of construction; the concessionaire raises the money and recovers it through user charges.
- Kamarajar Port Limited will separately spend an estimated Rs 450 crore on dredging.
What the Cabinet cleared
The Press Information Bureau release says the port’s existing terminal, rated at 0.8 million TEUs, handled about 0.7 million TEUs in 2025-26, or 88 per cent utilisation. The concessionaire will be picked through open global bidding, with environmental and other clearances to be obtained before the bid due date. Swarajya’s report of the decision carries the same figures and the same timetable. The project was already on paper in August, when DT Next reported the identical phase costs at proposal stage. That report also listed the scope: pile berths, container yards, internal roads, a customs gate complex and buildings on 111.19 acres, with 500 m of quay in Phase I and 400 m in Phase II.
Does this change what a contractor should plan for?
Not this season. The release counts construction from the date the concession is awarded, and that date depends on the bidding round, so no clock starts with this approval. Plan around the shape of the work instead.
The berth is the heavy-civil part. A pile berth usually means piling rigs working from the shore and from barges, then crawler cranes placing precast deck units, with a batching plant and transit mixers feeding the deck pours. That fleet stays on one site for the whole phase, which is the case for owning rather than hiring.
The yard behind it looks like earthwork but is mostly a compaction job. Stacked containers put heavy, concentrated loads on the ground, so the hours go to vibratory soil compactors, motor graders and the tipper fleet bringing in fill and aggregate from inland quarries. Dredging is the port’s own Rs 450 crore marine contract and uses dredgers, not land machines; our ports and dredging guide covers how those jobs are equipped.
Keep the headline in proportion. Rs 4,288.26 crore is the concessionaire’s whole project cost, including ship-to-shore cranes and yard handling equipment, not a civil works budget. The winner is its own client, so it may run the civil works in-house or award them as one EPC package. The ship-to-shore cranes are one of the machine classes named in the Rs 11,000 crore CIE manufacturing scheme the Cabinet cleared the same day, so who builds this terminal’s cranes is worth watching too.
Dates to note
- The bid call for the concession, which is the Opportunity Desk’s lane; the award will be news here.
- Phase I has to be finished within 24 months of the award date, with operations from month 25.
- Phase II runs from month 25 to month 48.
FAQ
How much will the Kamarajar Port second container terminal cost?
Rs 4,288.26 crore including GST: Rs 2,429.32 crore for Phase I and Rs 1,858.94 crore for Phase II, financed by the concessionaire. The port adds about Rs 450 crore for dredging.
Who will build it?
Not decided. The concessionaire will be chosen through open global bidding and will run the terminal for 40 years.
When does construction start?
No date yet. The 48-month construction period starts from the date the concession is awarded.