SRM Contractors has won an NHAI contract worth Rs 111.16 crore to build grade separators on the Porbandar-Jetpur section of NH-27 in Gujarat, with 18 months to finish once NHAI fixes the appointed date. For anyone who rents out cranes, concrete plant or piling kit in Saurashtra, this is a structures job with a short clock, and the contractor is based in Jammu, roughly the width of the country away.
Key numbers
- Value: Rs 111.16 crore, awarded by the National Highways Authority of India (company-stated in its exchange filing).
- Scope: grade separators at Rabarika Chowkdi on the Kutiyana bypass near Mal-Choliyana village and at Kutiyana village, plus a 2.20 km service road.
- Time: 18 months from the appointed date, which has not been announced.
- Tender estimate: NHAI put Rs 123.55 crore on the package when it floated it on 3 February 2026.
What SRM disclosed
SRM Contractors told BSE and NSE on 26 November, in a Regulation 30 filing received at 12:50 pm, that it had bagged the contract from NHAI. The filing calls it a domestic award and says no promoter or related party has an interest in it. Free Press Journal reported the same scope and value the same afternoon. We listed this tender on our Kutiyana grade separator tender page in September, when bids were due on 17 September after three corrigenda.
One caution on the numbers. Neither the filing nor the tender listing says whether its figure includes GST, so the gap between the Rs 123.55 crore estimate and the Rs 111.16 crore award should not be read as a confirmed bid discount.
Does this change what a contractor or hirer should line up?
Yes, if you work in Saurashtra. This is not a road-building contract with a structure or two attached. Apart from 2.20 km of service road, the money goes into concrete: foundations, piers or abutments, decks and the earth-filled approaches that lift traffic over or under the junction. That puts the weight on cranes for reinforcement cages and deck work, a batching plant with transit mixers and a concrete pump to keep pours on schedule, and excavators for foundation pits and any underpass box.
The filing does not say whether the foundations are piled or open, or whether decks use precast girders or cast-in-place slabs. Those two choices decide whether a piling rig and a heavy crawler crane are needed at all, so hire firms should wait for the design before quoting long rentals.
The approaches and the service road are where earthmoving plant earns its hours: soil and tandem compactors, a motor grader, tippers and a small paver. Our road construction equipment guide lists the classes involved.
Our read on own-versus-hire: SRM’s registered office is in Jammu, and its last contract we covered was landslide work in Uttarakhand. Moving cranes and concrete plant to Porbandar district costs real low-bed money for an 18-month job, so we would expect local hire for the heavy lifting and the concrete train. That is an inference, not something the company has said.
Dates to note
- The appointed date from NHAI starts the 18-month clock. Until then, no fleet moves.
- Gujarat’s monsoon months shut down most open foundation work, so a start in the next few weeks gives one dry season for substructure.
- Sub-contracts for piling, retaining walls or deck work, if SRM lets any, would follow the design approval.
FAQ
Who awarded SRM Contractors the Rs 111.16 crore contract?
The National Highways Authority of India, for grade separators and a 2.20 km service road on the Porbandar-Jetpur section of NH-27 in Gujarat.
How long does SRM have to finish the Kutiyana work?
18 months from the appointed date, according to the company’s filing. NHAI has not announced that date yet.
Which machines will a grade separator job like this need?
Mainly concrete and lifting plant: cranes, a batching plant, transit mixers, a concrete pump and excavators, with compactors and a grader on the approaches and the service road.
Pricing a crane or a concrete pump for structures work in Gujarat? Compare models, specs and dealer prices on DesiMachines, and check finance options before you commit to a purchase over hire.
Related on DesiMachines: SRM Contractors wins Rs 138.37 crore MoRTH landslide contract in Uttarakhand
Source: Free Press Journal
Machines, tenders and news for this industry: Road Construction