1150 kV Transmission Corridor: NCT Clears Rs 68,816 Crore West-East Grid Link

Reviewed by 4 min read
1150 kV Transmission Corridor: NCT Clears Rs 68,816 Crore West-East Grid Link

India’s transmission planners have cleared the country’s first 1150 kV transmission corridor, a scheme of about Rs 68,800 crore that will carry Rajasthan’s renewable power east to Chhattisgarh, Odisha and West Bengal. For equipment owners the voltage record is the least useful part. What matters is that the job splits into two very different kinds of site work, and neither starts until an award process that has not yet begun.

The work at a glance

  • Cleared by: the National Committee on Transmission (NCT) at its 45th meeting on 9 November, according to the minutes as reported by BusinessLine.
  • Estimated cost: Rs 68,816 crore in the minutes; Reuters put it at about Rs 68,800 crore.
  • Route named so far: a 1150 kV double-circuit line from Raigarh Kotra in Chhattisgarh through Rourkela in Odisha to Kolaghat in West Bengal, tied to a 6,000 MW feed from Rajasthan’s Bhadla zone.
  • Build time: about six years, according to Reuters.

What the committee cleared

Reuters reported the clearance on 11 November, and BusinessLine’s M Ramesh read the minutes the next day. Both put the scheme near Rs 68,800 crore and describe it as the highest transmission voltage India has attempted. The corridor was first worked up at a joint planning meeting of the Central Transmission Utility on 21 September. Those minutes size each 1150/400 kV transformer bank at 3,000 MVA, made up of three single-phase 1,000 MVA units.

The decision was not free of doubt. BusinessLine reports that expert member S R Narasimhan, a former head of Grid Controller of India, questioned the 7.64 per cent yearly peak-demand growth the studies assume and warned that the lines could run lightly loaded outside solar hours.

Which machines this work needs

Treat the corridor as two jobs. Each substation, at Raigarh Kotra, Rourkela and Kolaghat, is one large graded platform: dozers, 20-tonne-class excavators, tippers and soil compactors for months, then piling and a batching plant for transformer and reactor foundations. Single-phase transformer units of that rating are heavy, over-dimension lifts, so expect large crawler cranes on site for weeks at a stretch, almost always on hire.

The line is the opposite. It is hundreds of separate tower pits along the route, each a few days of digging, concreting and backfill before the crew moves on. That pattern suits backhoe loaders, small excavators and plate compactors that shift cheaply between locations, and it favours hire over purchase. Ground conditions change along the way too: harder plateau country is typical around Raigarh and Rourkela, while the delta soil near Kolaghat makes piled tower foundations more likely.

No line length appeared in the reports we read, so we have not worked out a per-km rate. Nor is it public whether the substations will be air-insulated or gas-insulated, which decides how much land, and therefore how much earthwork, each yard needs.

Our reading: this is a forward demand signal, not a reason to add machines this season. The dissent recorded in the minutes means the scope could still be phased or trimmed before anyone is awarded the work.

What follows next

  • Allocation of the scheme to an implementing company. Most inter-state lines of this size go through tariff-based bidding; the route for this one has not been announced.
  • The winning transmission company is an owner, not the fleet buyer. Machines get booked when it lets substation and line EPC packages.
  • Eastern India’s dry-season window, roughly October to May, will set when foundation crews can actually mobilise.

FAQ

Is the 1150 kV corridor approved for construction?

The National Committee on Transmission has cleared it. Allocation and award to an implementing company still have to happen before site work starts, and none has been announced.

How long will it take to build?

Reuters reports about six years. With the award still ahead, heavy civil work this season looks unlikely.

Which machines will the corridor need most?

Earthmoving and compaction plant for the substation platforms, heavy cranes for transformer and reactor lifts, and mobile backhoe and small excavator crews for tower foundations along the line.

Lining up transmission work? Compare crawler and mobile cranes for substation lifts, or size backhoe loaders for tower foundation crews before the packages are let.

Related on DesiMachines: Odisha’s Rs 15,948 crore 765 kV grid approval

Source: BusinessLine

Share this article:

Disclaimer: *All logos, trademarks, brand names, images, videos, documents, and product information displayed on DesiMachines are the property of their respective owners. DesiMachines is an independent aggregator working with OEMs, authorised dealers, channel partners, and publicly available sources. Display of any brand or content does not imply partnership or endorsement. Product details, specifications, prices, and availability are indicative and subject to change. Users should verify final details with the respective dealer or seller. DesiMachines is not liable for any inaccuracies or decisions made based on the information provided.

!

Let's get started

Disclaimer

Desi Machines is a platform where you can see and compare construction equipment. It showcases images, brochures, features, technical specifications, brand details & dealer information. All these are taken from respective brand websites, brochures, and other public resources. We do not claim ownership of these materials and strive to ensure their accuracy. However, the disparity may happen and we advise users to verify directly with respective brands and dealers. Desi Machines is not liable for any inaccuracies or reliance on the information provided. Use of this website is at your own discretion.

Read the full disclaimer

Compare