Suno Sabki, Chuno Apni.
Chat with us
Infrastructure & Projects

MEIL Wins Rs 3,373 Crore Upper Indravati Pumped Storage EPC as Odisha Clears Project

Reviewed by 4 min read
MEIL Wins Rs 3,373 Crore Upper Indravati Pumped Storage EPC as Odisha Clears Project

Odisha’s cabinet on Monday put a price on a job Megha Engineering & Infrastructures (MEIL) has held since July. The 600 MW Upper Indravati pumped storage project in Kalahandi will cost Rs 4,708.64 crore in all, and MEIL’s EPC bid is Rs 3,372.88 crore before GST. The July letter of intent carried no value, so this is the first time anyone outside OHPC has seen the contract number. For plant owners in western Odisha, that number is what turns a hydro headline into four-plus years of rock work.

The work at a glance

  • Project: 600 MW Upper Indravati pumped storage project (four units of 150 MW) at Ranibahal, Kalahandi district, executed through Odisha Hydro Power Corporation (OHPC).
  • Contractor: MEIL, selected as EPC contractor at Rs 3,372.88 crore, GST extra. OHPC issued the letter of intent in late July 2026.
  • Total cost: Rs 4,708.64 crore including GST, consultancy, land acquisition, forest clearance and interest during construction.
  • Money and date: 80:20 debt-equity. The state lends 80 per cent as a phased soft loan at the RBI repo rate; OHPC puts in 20 per cent from internal reserves. Commissioning is targeted for 2030-31.

What the cabinet decided

Pragativadi and Sambad English both reported that the cabinet approved three things together: the project cost, the choice of MEIL after tendering, and the funding plan. The plant is designed to deliver about 1,040 million units of peak power a year while drawing about 1,283 million units of off-peak power to pump water back up. MEIL’s own project page says the existing Indravati reservoir will serve as the upper reservoir, a new lower reservoir will be built near Ranibahal, and the powerhouse will be underground.

Which machines this work needs

Start with the split. At the standard 18 per cent, GST would take the EPC bid to roughly Rs 3,980 crore. That leaves roughly Rs 729 crore of the approved total for land, forest clearance, consultancy and interest. Those are costs that never reach a site. On the EPC side, the reversible pump-turbines, generators and electrical kit take a large slice too. So the civil money is a minority of the headline, but at this scale it still adds up to a lot of rock and concrete.

Because the upper reservoir already exists, the earthmoving sits in two places: the new lower reservoir and the underground works. An underground powerhouse means cavern and tunnel excavation, which pulls rock drills and drill jumbos, hydraulic excavators with breakers, wheel loaders for mucking, and dumpers on short, steep hauls. Concrete lining and the powerhouse structure need batching plants, transit mixers, shotcrete units and crawler cranes. The lower reservoir is an earthwork job for excavators, dozers, dumpers and soil compactors, though the dam type and height have not been published, so the size of that fleet cannot be read yet.

The likely pattern: a contractor of MEIL’s size usually self-performs the core underground work with its own plant, as on most big power construction jobs. Outside owners are more likely to win the edges, such as aggregate crushing, haulage, approach roads and the concrete supply chain. Kalahandi is remote, so a machine that goes there tends to stay for years. That favours owning over short hire for anyone who lands a long sub-contract, and it makes spares stocking a real cost to price in.

What follows next

  • The signed EPC agreement and a start date, which set the clock on the 2030-31 target.
  • Any published layout: tunnel lengths, cavern size and the lower dam’s type and height.
  • MEIL’s sub-contract packages for tunnelling, crushing and haulage, where the open-market machine demand sits.

FAQ

Who is building the Upper Indravati pumped storage project?

Megha Engineering & Infrastructures Ltd is the EPC contractor. Odisha’s cabinet approved its selection at a bid price of Rs 3,372.88 crore, excluding GST, for OHPC.

Why is the total cost higher than the EPC price?

The Rs 4,708.64 crore total includes GST, consultancy, land acquisition, forest clearance and interest during construction on top of the contract price.

When will the project be finished?

The cabinet set commissioning for the 2030-31 financial year. No construction start date has been announced yet.

Bidding for hydro or tunnel sub-work? See what tunnel and bridge jobs pull in machines, then line up excavator and crane options and check equipment finance before you commit a fleet to a four-year site.

Related on DesiMachines: KEC International wins a Rs 1,014 crore 765 kV line for a pumped storage project

Source: Sambad English

Share this article:

Disclaimer: *All logos, trademarks, brand names, images, videos, documents, and product information displayed on DesiMachines are the property of their respective owners. DesiMachines is an independent aggregator working with OEMs, authorised dealers, channel partners, and publicly available sources. Display of any brand or content does not imply partnership or endorsement. Product details, specifications, prices, and availability are indicative and subject to change. Users should verify final details with the respective dealer or seller. DesiMachines is not liable for any inaccuracies or decisions made based on the information provided.

!

Let's get started

Disclaimer

Desi Machines is a platform where you can see and compare construction equipment. It showcases images, brochures, features, technical specifications, brand details & dealer information. All these are taken from respective brand websites, brochures, and other public resources. We do not claim ownership of these materials and strive to ensure their accuracy. However, the disparity may happen and we advise users to verify directly with respective brands and dealers. Desi Machines is not liable for any inaccuracies or reliance on the information provided. Use of this website is at your own discretion.

Read the full disclaimer

Compare