Kanpur to Kabrai is getting a 117.7 km access-controlled greenfield highway, and NHAI has the Rs 5,757.23 crore package open for bids until 6 October 2026.
Two sections in one contract
The tender joins two pieces of work on the Kanpur-Kabrai route through Bundelkhand. Section 1 is the new four/six-lane access-controlled greenfield highway, starting at km 0.000 on the Kanpur Ring Road and running to km 117.700 near Kabrai in Mahoba district. Section 2 is overlay, strengthening and road safety improvement on the existing Kanpur-Kabrai stretch of NH-34 from km 7.430 to km 130.100, the road that will carry traffic while the new one is built.
It is let on the DBFOT pattern, so the concessionaire designs, builds, finances, operates and transfers. NHAI’s Kanpur project unit handles it, and the file reference points to the Hamirpur spur. The tender dates from 24 December 2025 and has been extended since.
Who should look at it
The main bidder will be a large highway developer. The size of the earthwork is what matters to everyone else: 117 km of greenfield formation across the Yamuna and Betwa river country means borrow areas, big fill quantities and a lot of cross-drainage structures. Contractors and fleet owners in Kanpur, Hamirpur, Mahoba and Banda, especially those who worked on the Bundelkhand Expressway, are well placed for sublet packages.
EMD and fee
EMD is Rs 57,57,00,000, which is 1% of the estimate, and the tender fee is Rs 5,80,000.
Plant on a job this size
Earthwork is the long pole: excavators at borrow pits, several hundred tipper trips a day, and dozers, motor graders and vibratory rollers on the embankment. The overlay section needs a hot mix plant, sensor pavers and tandem and pneumatic rollers. River bridges and interchanges add piling rigs, cranes and batching plants with transit mixers.
Key facts
Tender ID
2025_NHAI_260322_1
Reference no.
NHAI/KNP/KANPUR KABRAI/ HamirpurSpur
Issuing authority
National Highways Authority of India, PIU Kanpur
Location
Kanpur Ring Road to Kabrai, with NH-34 km 7.430 to 130.100, Uttar Pradesh
What does the Kanpur Kabrai highway tender include?
A 117.7 km four/six-lane access-controlled greenfield highway from the Kanpur Ring Road to near Kabrai, plus overlay and road safety work on the existing NH-34 from km 7.430 to km 130.100.
What contract model applies?
DBFOT: design, build, finance, operate and transfer.
How much is the EMD?
Rs 57,57,00,000, or 1% of the Rs 5,757.23 crore estimate. The tender fee is Rs 5,80,000.
What is the bid deadline?
6 October 2026 at 11:00 AM, with bid opening on 7 October 2026 at 11:30 AM.
Tender details are summarised for convenience and may change. Always verify the latest dates, terms and documents on the official tendering portal before bidding. DesiMachines is not responsible for changes made by the issuing authority.
Bidding with your own machines?Tenders often ask for machine papers such as the RC, insurance and invoice. Keep them in one private place on My Machine and get a reminder before insurance or service falls due. Free.
Desi Machines is a platform where you can see and compare construction equipment. It showcases images, brochures, features, technical specifications, brand details & dealer information. All these are taken from respective brand websites, brochures, and other public resources. We do not claim ownership of these materials and strive to ensure their accuracy. However, the disparity may happen and we advise users to verify directly with respective brands and dealers. Desi Machines is not liable for any inaccuracies or reliance on the information provided. Use of this website is at your own discretion.