16.70 km of the Old AT Road between Laipuli and the Makum ROB in Tinsukia was never finished, and Assam PWD has put the balance work back out at ₹33.02 crore, closing at 2:00 PM on 17 November 2026.
Picking up 16.70 km somebody else left
The notice is for balance work on the improvement and upgradation of the Old AT Road, the former NH-37, from chainage 636.80 km at Laipuli to chainage 653.50 km at the Makum ROB. That is 16.70 km in Tinsukia district, tendered under Asom Mala 3.0 for 2025-26, reference CE/DEV/ASOMMALA3.0/14/25-26/17 dated 5 November 2026.
Balance work changes how you bid. Part of the road is already built, part is half built, and the schedule reflects what is left rather than a clean greenfield quantity. A site visit matters more here than on a new road, because what the previous contractor actually completed decides whether the rates make sense.
A ten-day window
Bidding closes on 17 November with opening half an hour later the same afternoon, so there is very little time. The value is ₹33,01,57,000 with an EMD of ₹66,03,000 at 2 per cent and a fee of ₹20,000. The form of contract is item rate and the completion period is 540 days.
The Old AT Road is the working road through upper Assam’s tea and oil belt, and it stays busy while you work on it. Plan on half-width working, which means backhoe loaders and smaller machines for the shoulder and drain work, with excavators on the stretches you can close.
Pavement goes down with a motor grader and compactors. Tinsukia gets heavy, long rain, so the 540 days really comes down to two dry windows: get the sub-base and drainage finished in the first one. Culvert repairs along the route need concrete mixers rather than a plant.
Key facts
Tender ID
2026_PWD_54857_1
Reference no.
CE/DEV/ASOMMALA3.0/14/25-26/17 Dt.05.11.26
Issuing authority
Public Works Roads Department, Government of Assam
Location
Old AT Road (Old NH-37), Ch. 636.80 km (Laipuli) to Ch. 653.50 km (Makum ROB), Tinsukia district, Assam
Balance work for the improvement and upgradation of the Old AT Road, formerly NH-37, from Ch. 636.80 km at Laipuli to Ch. 653.50 km at the Makum ROB in Tinsukia district, a length of 16.70 km, under Asom Mala 3.0.
What does balance work mean for a bidder?
Part of the road is already built, so the schedule covers only what is left. The quantities depend on what the earlier contractor finished, which makes a site visit important before you price the bid.
What is the value and EMD?
₹33.02 crore, shown as ₹33,01,57,000, with an EMD of ₹66,03,000 at 2 per cent and a tender fee of ₹20,000.
What are the dates and the work period?
Bids close at 2:00 PM on 17 November 2026 and open at 2:30 PM the same day. The completion period is 540 days.
Tender details are summarised for convenience and may change. Always verify the latest dates, terms and documents on the official tendering portal before bidding. DesiMachines is not responsible for changes made by the issuing authority.
Bidding with your own machines?Tenders often ask for machine papers such as the RC, insurance and invoice. Keep them in one private place on My Machine and get a reminder before insurance or service falls due. Free.
Desi Machines is a platform where you can see and compare construction equipment. It showcases images, brochures, features, technical specifications, brand details & dealer information. All these are taken from respective brand websites, brochures, and other public resources. We do not claim ownership of these materials and strive to ensure their accuracy. However, the disparity may happen and we advise users to verify directly with respective brands and dealers. Desi Machines is not liable for any inaccuracies or reliance on the information provided. Use of this website is at your own discretion.