Both main canals of the Satiguda Medium Irrigation Project in Malkangiri are getting concrete lining, repaired structures and strengthened embankments for ₹42.02 crore, and the Satiguda canal lining tender closes at 5:30 PM on 1 December 2026.
Thirty kilometres on the right bank, twenty seven on the left
The scope runs from RD 0.00 km to RD 30.688 km of the right main canal and from RD 0.00 km to RD 27.100 km of the left main canal, which is 57.788 km of working front in total. On that length the contractor provides cement concrete lining, renovates structures, and re-sections and strengthens the canal embankment. The Earth Dam Division at Chitrakonda is executing it under the Chief Construction Engineer, Potteru Irrigation Project, Balimela, reference CCE-PIP-BML-19/2026-27.
The item list in the notice tells you what the days will look like: earth work, filling foundation and plinth with sand and excavated material, M-15 cement concrete, RCC with HYSD bar, centering and shuttering, spreading of metal and sand, and fixing of pressure relief valves. Lining panels and valves on an old canal mean careful survey work before any concrete goes down.
Percentage rate bidding over two years
The portal lists the value at ₹42,01,68,648 with an EMD of ₹42,01,700, which is 1 per cent, and a fee of ₹10,000. The form of contract is percentage, so you bid a percentage above or below the departmental schedule of rates rather than quoting item by item. That suits a contractor who knows the local rate book well and carries low overheads. The period is 731 days.
With 57.788 km of canal to cover in two monsoon-bound years, the sensible shape is four or five small crews working different reaches rather than one large camp. Each needs an excavator for re-sectioning and spoil, a backhoe loader moving along the bank for structures and valve pits, and a compactor for the embankment. Lining concrete comes from site mixers placed every few kilometres, because hauling wet mix down a canal bund wastes most of your day.
Malkangiri sits a long way from the nearest machine dealer, so spares holding and a travelling mechanic matter more than headline machine specs. Canal lining also stops dead in the rains, which is why the department has allowed 731 days for what looks like a one-season quantity.
Key facts
Tender ID
2026_CCEBA_145850_1
Reference no.
CCE-PIP-BML-19/2026-27
Issuing authority
Chief Construction Engineer, Potteru Irrigation Project, Balimela, through the Earth Dam Division, Chitrakonda
What length of canal does the Satiguda canal lining tender cover?
RD 0.00 km to RD 30.688 km of the right main canal and RD 0.00 km to RD 27.100 km of the left main canal of the Satiguda Medium Irrigation Project, 57.788 km in total.
What work is included?
Cement concrete lining, renovation of structures, and re-sectioning and strengthening of the canal embankment, with earth work, M-15 concrete, RCC with HYSD bar, centering and shuttering and pressure relief valves among the listed items.
What does a percentage contract mean for bidding?
You quote a percentage above or below the departmental schedule of rates instead of pricing each item. The estimate is ₹42,01,68,648, the EMD is ₹42,01,700 and the fee is ₹10,000.
What are the dates?
Bids close at 5:30 PM on 1 December 2026 and open at 11:30 AM on 2 December 2026. The completion period is 731 days.
Tender details are summarised for convenience and may change. Always verify the latest dates, terms and documents on the official tendering portal before bidding. DesiMachines is not responsible for changes made by the issuing authority.
Bidding with your own machines?Tenders often ask for machine papers such as the RC, insurance and invoice. Keep them in one private place on My Machine and get a reminder before insurance or service falls due. Free.
Desi Machines is a platform where you can see and compare construction equipment. It showcases images, brochures, features, technical specifications, brand details & dealer information. All these are taken from respective brand websites, brochures, and other public resources. We do not claim ownership of these materials and strive to ensure their accuracy. However, the disparity may happen and we advise users to verify directly with respective brands and dealers. Desi Machines is not liable for any inaccuracies or reliance on the information provided. Use of this website is at your own discretion.