Bihar’s cabinet on Tuesday approved a revised cost of Rs 4,572.53 crore for the Bakhtiyarpur-Tajpur Ganga bridge and its approach roads, and agreed to put Rs 1,834.305 crore of state money behind finishing it. This is not a new project. It is a long-running, half-built crossing that needed more money to get to the other bank. For machine owners around Patna and Samastipur, the remaining work is a concrete job, and the new money keeps that concrete train funded.
Key numbers
- Revised cost: Rs 4,572.53 crore for the four-lane Ganga bridge and approach road project linking Bakhtiyarpur (Patna) with Tajpur (Samastipur).
- Scope: a 5.52 km bridge over the Ganga plus 45.40 km of approach road, about 50.9 km in all.
- State support: Rs 1,834.305 crore from the state government to complete the work physically, including a current instalment of Rs 263.58 crore.
- Decision: one of 31 items cleared by the Bihar cabinet under Chief Minister Samrat Choudhary on 10 November 2026.
What the cabinet approved
Dainik Jagran and Prabhat Khabar both carried the decision with the same figures. Jagran reports that this is the third administrative approval for a revised cost on the project. Prabhat Khabar and 22Scope describe the Rs 1,834.305 crore as a loan from the state to the construction company. Neither desk published the split between the bridge and the approach road, or the cost at the previous approval, so the size of the increase cannot be worked out from this decision alone.
Does this change what a contractor should buy?
Mostly it changes what gets hired, and for how long. Spread over the full 50.9 km, the revised cost works out to roughly Rs 90 crore per km. That is a structures rate, not a road rate, and the crossing is the likely reason. With the remaining work described in terms of deck segments and piers, the open machine demand is in the superstructure, not in earthwork.
In April, a site review by Bihar’s Chief Secretary, as reported by Patna Press, put the remaining work at 438 deck segments, with a target of 40 segments cast a month and work up to pier P-29 due by May 2027. He also asked for more casting equipment on site. A precast segment job like that runs on a steady fleet: batching plants, transit mixers shuttling to the casting yard, gantry and crawler cranes to handle segments, and the launching girders that set them on the piers. The girders are specialist kit the contractor already owns. The yard cranes, mixers and pumps are where local owners and rental firms usually get a look in.
Whatever approach-road work remains is a different, smaller ask. It pulls pavers, rollers and short-haul tippers in bursts, the usual road construction equipment mix, but for weeks, not years. Our reading: the state stepping in with a loan means the money risk on this job has eased, which matters to anyone being paid as a sub-hirer. A stalled river bridge is where hire bills go unpaid. The usual caution applies. The Ganga sets the calendar, and river works slow sharply in the monsoon months, so plan utilisation on the dry season, not twelve months.
For contractors tracking similar work across bridge and tunnel projects, the bigger point is supply. When a crossing this size finishes, its cranes and concrete plant come back onto the Bihar hire market at once.
Dates to note
- Release of the Rs 263.58 crore current instalment, which shows whether site work picks up this dry season.
- May 2027, the target reported in April for work up to pier P-29.
- The monsoon window from June, when river-side work slows and machines idle.
Running cranes or concrete plant in Bihar? Compare crane and transit mixer options before you commit a fleet to a river job that pauses every monsoon.
FAQ
What is the revised cost of the Bakhtiyarpur-Tajpur bridge?
The Bihar cabinet approved a revised cost of Rs 4,572.53 crore on 10 November 2026 for the four-lane Ganga bridge and its approach roads.
How long is the Bakhtiyarpur-Tajpur bridge?
The bridge over the Ganga is 5.52 km long, and the approach road is 45.40 km, according to the cabinet decision as reported.
Who is paying for the extra cost?
The state government will provide Rs 1,834.305 crore to complete the work, including a current instalment of Rs 263.58 crore. Regional desks describe it as a loan to the construction company.