IRB Infrastructure has about 17,071 lane km of highway under its name, yet as read on 18 November 2026 it publishes no vendor registration page or portal anywhere on irb.co.in. IRB vendor registration happens inside each deal: a supplier or hire firm is checked at the tender and contract stage and must accept IRB’s Intermediaries Code of Conduct, dated 21 December 2025. IRB spent Rs 28.60 crore on hire charges in 2025-26, and its construction order book had shrunk to Rs 1,200 crore by 30 September 2026, against Rs 42,100 crore of highway operation and maintenance.

Most machine owners picture IRB the way they picture L&T or Afcons: a large builder with a supplier portal and a steady stream of site work. The 2025-26 figures say otherwise. IRB has finished what it calls its asset creation phase and now earns mostly from tolls, operation and maintenance (O&M) contracts and its two infrastructure investment trusts (InvITs). The facts below come from irb.co.in, the Intermediaries Code of Conduct, the Integrated Annual Report 2025-26 and the investor presentation for the September 2026 quarter.

Is there an IRB vendor registration portal?

No. The menu of irb.co.in has no vendor or tender link, and a search of the site for vendor, tender and similar terms returned no supplier page on 18 November 2026. The contact page has an enquiry form, and its corporate enquiries option is the nearest fit for a supplier.

What IRB does publish is a description of how it onboards suppliers. The integrated report says tender meetings, vendor onboarding and contract finalisation are “aligned with the Intermediaries Code of Conduct”, and that all new suppliers are assessed against commercial, technical, safety, environmental and compliance requirements before engagement. Registration and the first order arrive together. Compare that with L&T’s open Partner Portal for hire firms and the Afcons Smart SCM vendor portal, where you can sign up before any enquiry exists.

Question What IRB publishes (as read on 18 November 2026)
Vendor portal or form None on irb.co.in
Supplier code Intermediaries Code of Conduct, R0, 21 December 2025
Who it covers Vendors, contractors, sub-contractors, suppliers, consultants and others engaged by the IRB group
When you are checked At onboarding and contract award, then reviewed every year
Fee, class, validity Not published
Contract value that triggers full due diligence Left blank in the published code (“INR XX”)
Corporate office IRB Complex, Chandivali, Andheri (East), Mumbai

What the Intermediaries Code of Conduct asks of a hire firm

The IRB Intermediaries Code of Conduct is 12 pages long and applies across IRB, its subsidiaries, associates and joint ventures. A firm that hires out an excavator with an operator to an IRB site is a vendor under its own wording.

The core rules are short. No bribes or kickbacks, and nothing of value to IRB staff. Disclose any link with a current or past IRB employee or their family. Follow labour and human rights law, keep a safe workplace, and pass the same rules down to your own sub-contractors. IRB’s anti-bribery policy goes further: no gifts or hospitality of any kind or amount to or from an intermediary where it might look linked to a procurement or bidding process, and any gift over Rs 25,000 needs the prior approval of the chairman and managing director.

Larger engagements get a due diligence check by the compliance officer, the company’s Senior Manager, Legal. The published code sets the value thresholds as “INR XX lakh” and “INR XX Crores”, so the actual cut-offs are not public. Above them you fill in Annexure A, a 13-point questionnaire on environmental compliance, waste, water, health and safety, labour compliance, child and forced labour, wages and your own policies, signed by an authorised person. IRB also searches public records on you and asks other firms about your reputation. The CEO approves or rejects.

Two outcomes matter. A firm on the US, UK, EU or UN sanctions lists is ruled out. A firm that fails the diligence becomes a “Restricted Intermediary”, and any later approval for it must go to the CEO or CMD. Every existing engagement is reviewed each year, and a breach can end the contract.

IRB’s Health, Safety and Welfare Policy adds the site rules a machine owner will feel first. Contractors must declare the hazards of their equipment before work starts, and IRB commits to checking machines, vehicles and safety equipment at least monthly.

How much IRB buys, and how much of it is hire

The figures are consolidated, from the Integrated Annual Report 2025-26, the latest audited numbers on irb.co.in as of November 2026.

Measure (consolidated) FY2024-25 FY2025-26
Hire charges Rs 24.55 crore Rs 28.60 crore
Sub-contracting and security expenses Rs 62.56 crore Rs 55.93 crore
Contract expenses Rs 2,084.56 crore Rs 1,697.48 crore
Inputs sourced directly from MSMEs and small producers 22% 18%
Days of accounts payable 47.52 25.57
Unpaid principal owed to micro and small suppliers at year end Rs 115.59 crore Rs 52.82 crore
Plant and machinery at cost, year end Rs 224.67 crore Rs 122.19 crore

The sustainability section counts 2,041 active suppliers and Rs 1,365.68 crore of procurement in 2025-26. It is concentrated: 11 suppliers, each at 2% or more of spend, took about 51% of it, and steel alone was about 11%. A local hire firm sits in the long tail.

Payment is the bright spot. Days of payables fell from about 48 to about 26 in one year. The accounts state normal terms of 90 days, and no interest was due on micro and small enterprise dues at 31 March 2026. Section 15 of the MSMED Act, 2006 caps the agreed credit period for a micro or small supplier at 45 days, but only a firm with Udyam registration can claim it.

The last row is worth a pause. IRB’s own plant and machinery at cost fell by almost half during the year, after disposals of Rs 116.21 crore. The accounts do not say which machines went. A smaller owned fleet does not guarantee more hire, but it is the trend to watch.

Who builds IRB’s roads: Modern Road Makers and the InvITs

IRB names Modern Road Makers Private Limited as its EPC arm. The September 2026 presentation says construction and O&M of the four wholly owned assets are carried out by IRB, and that construction and O&M for the Private InvIT’s projects is done by IRB on a fixed price basis. Tolling and maintenance run in-house with what the company calls its own equipment bank, and stone aggregate comes from leased mines near the projects.

So the question for a machine owner is where the remaining construction sits. As of 30 September 2026 the EPC order book was Rs 1,200 crore, all of it executable within two years. These are the projects the presentation lists as still building.

Project State Lane km Status (30 September 2026)
Pathankot-Mandi, Package 1 (HAM, NH 154) Himachal Pradesh 115 Under construction
Chittoor-Thachur, Package 4 (HAM, NH 716B) Tamil Nadu 120 Under construction
Samakhiyali-Santalpur (BOT, Private InvIT) Gujarat 545 Tolling and construction

A new highway package like Chittoor-Thachur needs bulk earthwork and layer-by-layer compaction. A 3,000 mm blade grader such as the Mahindra Roadmaster G90 and an 11,200 kg soil compactor such as the SANY SSR110C-10 PRO are the kind of machines an embankment crew hires by the month. The O&M book is larger but slower: only Rs 2,800 crore of it is executable in the next two years, on stretches IRB already tolls and largely maintains with its own crews.

IRB’s new work arrives through NHAI concessions, and its September 2026 presentation lists toll-operate-transfer (TOT) stretches and BOT projects as the pipeline. A TOT win hands over a road that is already built; a BOT or hybrid annuity (HAM) win means fresh construction. Watch the awards on current highway tenders and contract awards and approach a new site early. For how the government side qualifies its own contractors, see NHAI contractor registration, and for where IRB stands among highway builders, the top EPC companies building India’s highways.

Before you approach an IRB site: a checklist

  • Get a Udyam registration before your first invoice, so the MSMED Act’s 45-day limit and interest rules cover you.
  • Read the Intermediaries Code of Conduct and keep a signed copy of its Annexure A questionnaire answered for your firm.
  • Write down a basic safety policy and an anti-bribery policy; the questionnaire asks whether you have them.
  • Prepare a hazard note and fitness record for every machine, since IRB asks contractors to declare equipment hazards before work starts.
  • Declare any family or past-employment link with IRB staff in writing at the first meeting.
  • Offer no gift of any size to anyone handling an IRB order.
  • Approach the project office at Pathankot-Mandi, Chittoor-Thachur or Samakhiyali-Santalpur, or send a corporate enquiry through the contact page at irb.co.in.
  • Size any new machine EMI on equipment finance against a 90-day payment term, the normal term in IRB’s accounts.

Figures come from irb.co.in, the IRB Intermediaries Code of Conduct (R0, 21 December 2025), IRB’s Anti-Bribery and Health, Safety and Welfare policies (14 August 2025), the Integrated Annual Report 2025-26 and the investor presentation for the quarter ended 30 September 2026, as read on 18 November 2026. Machine specifications are as listed in November 2026 and vary by variant. Supplier terms and project status change. Confirm the current position with IRB or the project’s official source before you quote or commit a machine. DesiMachines is not liable for decisions taken on information that may have changed after publication.