A footing pit 1.8 m square and 1.5 m deep holds 4.86 m³ of earth, and that one sum is the whole method in small: excavation quantity is the length × breadth × depth of the hole, measured as the ground stood before it was dug. Indian works measure it under IS 1200 (Part 1), which pays only for the authorised dimensions, in cubic metres, with nothing added for the soil swelling once it is loose.

The hard part is deciding which length, breadth and depth to use. Working space around a footing, extra width in a deep trench, sloping sides in a basement and the uneven ground of a road cutting all change the answer. This guide works through each case in m³ and cft, then turns the bank volume into tipper trips and backfill. It covers quantity only. The money side, what to charge per cubic metre, is in the guide to the excavation rate per cubic meter.

How do you calculate excavation quantity?

Multiply the plan area of the excavation by its depth. For a pit or trench with straight sides that is simply length × breadth × depth. For anything with sloping sides or uneven ground you work out areas at several levels or sections and combine them with a formula, which the sections below show.

Three rules from IS 1200 (Part 1):1992 decide what goes into that sum. Clause 4.1 says earthwork is measured in cubic metres, from the authorised dimensions, “without allowance for increase in bulk”. Clause 2.3 says each dimension is taken to the nearest 0.01 m and the volume worked out to the nearest 0.01 m³. And where the ground is not level, clause 4.2 says levels are taken before the work starts and again after it is finished, and the quantity is computed from the two sets of levels.

So the quantity you bill is the hole, not the heap. One cubic metre in the ground is called a bank cubic metre. Once dug it becomes more than a cubic metre of loose soil, and the contract pays for the smaller number.

Excavation quantity formulas by shape
Shape of the excavation Formula Where it is used
Rectangular pit with vertical sides V = L × B × D Footing pits, sumps, small tanks
Trench of uniform width V = centre-line length × B × D Wall foundations, pipe and cable trenches
Pit with sloping sides (frustum) V = D/6 × (Atop + 4Amid + Abottom) Basements, ponds, deep pits
Long cutting, cross-sections at equal spacing d (trapezoidal rule) V = d × [(A1 + An)/2 + A2 + … + An−1] Road and canal cutting
Long cutting, odd number of sections (prismoidal rule) V = d/3 × [A1 + An + 4(even sections) + 2(odd sections)] Road and canal cutting where a closer figure is wanted
Level cross-section of a cutting A = (b + s × h) × h b = bed or formation width, h = depth at the centre, s = side slope (horizontal per 1 vertical)

Which dimensions does IS 1200 let you measure?

The drawing gives the size of the footing or wall. The pit you dig is usually bigger, and the standard says how much bigger can be paid for.

Working space. Clause 4.2.5 covers work that needs formwork, a damp-proof covering, protective masonry, or workers standing outside it. For these, the quantity is the authorised working space or what was actually dug, whichever is less. Where the contract does not set the working space, clause 4.2.5.1 allows 600 mm measured from the face of the substructure at its lowest level.

Deep trenches. For foundation trenches deeper than 1 m, clause 4.8.2 adds 50 mm per metre of depth on each side to the specified width. A 1.2 m deep trench therefore gets 60 mm extra on each side.

Stages of depth. Clause 4.2.3 measures excavation in stages of 1.5 m, stating the level each stage starts from, because deeper soil costs more to throw out. Clause 5.2 includes the first 1.5 m of lift in the main item and counts extra lift in further steps of 1.5 m. The companion standard for machine work, IS 1200 (Part 27):1992 on earthwork by mechanical appliances, says lift is not measured separately at all.

How IS 1200 (Part 1) names and measures each kind of excavation
Item Limits in the standard Unit
Trenches for foundations, pipes and cables Not over 1.5 m wide m³
Shafts, wells, cesspits and the like Not over 10 m² on plan m³
Excavation over areas Over 1.5 m wide and over 10 m² on plan, deeper than 300 mm m³
Surface excavation Over 1.5 m wide and over 10 m² on plan, not over 300 mm deep m²
Post holes Each not over 0.5 m³ Number
Return, fill and ram Layers not over 200 mm m³

Some things are never paid separately. Clause 2.6 lists setting out, site clearance, unauthorised battering or benching, steps left in the sides of deep excavation, removing small slips, and bailing out rainwater. If the soil is mixed with rock, clause 4.2 measures the whole quantity first, then stacks the hard rock and deducts an agreed percentage for voids. IS 1200 (Part 27) fixes that deduction at 50 percent for ordinary rock dug by machine. The full text of IS 1200 (Part 1):1992 is short and worth reading once before you prepare a bill.

Worked example: footing pits for a house in m³ and cft

Take a small house on 12 isolated footings. Each footing is 1.5 m × 1.5 m, sitting on a PCC bed (plain cement concrete levelling course) that projects 150 mm all round, so the bed is 1.8 m × 1.8 m. The bottom of the PCC is 1.5 m below ground level.

If the pit is dug to the size of the PCC bed, one pit is 1.8 × 1.8 × 1.5 = 4.86 m³. Twelve pits come to 58.32 m³.

If the footing sides are shuttered and the contract allows the IS 1200 working space of 600 mm from the face of the footing, the pit becomes 1.5 + 0.6 + 0.6 = 2.7 m square. One pit is 2.7 × 2.7 × 1.5 = 10.94 m³, and twelve come to 131.22 m³. That is more than double the first figure for the same footings, which is why the working space must be agreed in writing before the machine starts.

Cross-section diagram of a footing pit for excavation quantity calculation, showing a 1.5 m footing on a 1.8 m PCC bed, 600 mm working space on each side giving a 2.7 m pit, and 1.5 m depth
Figure 1. One footing pit measured two ways (section, not to scale). The working space of 600 mm from the footing face is the IS 1200 (Part 1) default under clause 4.2.5.1; your contract may set a different figure.

To turn cubic metres into cubic feet, multiply by 35.315. The small pit is 4.86 × 35.315 = about 171.6 cft, and the twelve small pits about 2,060 cft. The large pits are about 386 cft each and 4,634 cft for twelve.

Many sites measure in feet from the start. A pit 6 ft × 6 ft × 5 ft deep is 6 × 6 × 5 = 180 cft. Divide by 35.315 and it is 5.10 m³. Do the sum in one unit throughout and convert only at the end, so rounding does not creep in.

The concrete that goes back into these pits is worked out in the guide to footing concrete calculation. Pits of this size are usually dug by a backhoe loader such as the JCB 3DX or the JCB 2DX and trimmed by hand to level. If you are choosing a machine for this kind of work, compare backhoe loader models and their digging depths and talk to a dealer near your site.

How do you calculate excavation for a wall foundation trench?

Use the centre-line method: total length of the trench along its centre line × width × depth.

Say a house has outer walls whose centre lines form a rectangle 15 m × 9 m. The centre-line length is 2 × (15 + 9) = 48 m. A trench 0.9 m wide and 1.2 m deep along it holds 48 × 0.9 × 1.2 = 51.84 m³. For a closed rectangle this is exact, because what is gained at the outer corners is lost at the inner ones.

Inner walls need one correction. Add a 9 m cross wall that meets both long walls. Where it meets each one, half the trench width is already counted in the long wall’s trench, so take off half the width at each junction: 48 + 9 − (2 × 0.45) = 56.1 m. The trench volume is 56.1 × 0.9 × 1.2 = 60.59 m³, or about 2,140 cft.

Now apply clause 4.8.2, because the trench is deeper than 1 m. The width becomes 0.9 + 2 × 0.06 = 1.02 m, the junction deduction becomes 1.02 m in total, and the volume is 55.98 × 1.02 × 1.2 = 68.52 m³. The allowance adds about 7.9 m³ to this one small house. Narrow trenches like this suit a mini excavator such as the JCB 30 PLUS or the Tata Hitachi NX30, with the full range under mini excavators.

How do you calculate a pit or basement with sloping sides?

In soft soil the sides of a deep pit are cut back to a slope so they do not fall in. The pit is then wider at the top than at the bottom, and L × B × D no longer works. Use the prismoidal formula: V = D/6 × (top area + 4 × middle area + bottom area). For a pit with straight sloping sides this formula gives the exact volume.

Take a basement whose floor is 10 m × 8 m, dug 3 m deep with side slopes of 1:1 (1 m out for every 1 m down). At ground level each side has moved out 3 m, so the top is 16 m × 14 m.

Basement 10 m × 8 m at the bottom, 3 m deep, side slopes 1:1
Level Size Area
Bottom (3.0 m deep) 10 m × 8 m 80 m²
Middle (1.5 m deep) 13 m × 11 m 143 m²
Top (ground level) 16 m × 14 m 224 m²

V = 3/6 × (80 + 4 × 143 + 224) = 0.5 × 876 = 438 m³.

Two shortcuts are common and both miss. Averaging the top and bottom areas gives 3 × (80 + 224)/2 = 456 m³, which is 18 m³ too high. Using the middle area alone gives 3 × 143 = 429 m³, which is 9 m³ too low. The formula is called prismoidal because it is the volume of a prismatoid, a solid with two parallel flat ends, and the same prismatoid volume formula is used in geometry.

Because IS 1200 measures in 1.5 m stages, split the same pit at 1.5 m. The top stage, from ground level down to 1.5 m, is 1.5/6 × (224 + 4 × 181.25 + 143) = 273 m³. The bottom stage, from 1.5 m to 3 m, is 1.5/6 × (143 + 4 × 109.25 + 80) = 165 m³. Together they make the same 438 m³, and on manual work the bottom 165 m³ carries the extra lift. At this size the pit is “excavation over areas” under the standard, and a 20-tonne class machine such as the Tata Hitachi EX 210 Infra is the usual choice.

What is the trapezoidal and prismoidal formula for road and canal cutting?

A road or canal in cutting is measured from cross-sections taken at equal spacing along its length, often every 20 m or 30 m. Work out the area of each section, then combine them.

For a level cross-section with formation width b, centre depth h and side slope s horizontal to 1 vertical, the area is (b + s × h) × h. Take a road cutting with a 10 m formation and 1:1 side slopes, sections every 20 m:

Road cutting: cross-sections at 20 m spacing, 10 m formation, side slopes 1:1
Section Chainage Depth of cut h Area (10 + h) × h
1 0 m 0.8 m 8.64 m²
2 20 m 1.2 m 13.44 m²
3 40 m 2.0 m 24.00 m²
4 60 m 1.6 m 18.56 m²
5 80 m 0.8 m 8.64 m²

Trapezoidal formula (also called the average end area method): V = d × [(first + last)/2 + all the sections in between]. Here V = 20 × [(8.64 + 8.64)/2 + 13.44 + 24.00 + 18.56] = 20 × 64.64 = 1,292.80 m³.

Prismoidal formula: V = d/3 × [first + last + 4 × (even-numbered sections) + 2 × (odd-numbered sections in between)]. It needs an odd number of sections; if you have an even number, work the last strip separately with the trapezoidal formula. Here V = 20/3 × [8.64 + 8.64 + 4 × (13.44 + 18.56) + 2 × 24.00] = 20/3 × 193.28 = 1,288.53 m³.

The two differ by 4.27 m³ over 80 m, about a third of a percent. The trapezoidal figure usually comes out a little high on cuttings that change depth, so contracts state which method is to be used. On a long highway package the gap is real money; on a farm road it rarely matters. Side slopes and drains along the cutting are covered in the guide to side drains in road construction.

How much does soil swell once it is dug?

Soil bulks up when it is dug because air gets in between the lumps. The quantity in the bill stays in bank m³, but the tippers carry loose m³, so you need the factor between the two.

The US Army field manual TM 3-34.62, Earthmoving Operations (June 2012), gives average factors in its Table 1-1. They are averages for common materials, and real soil shifts with moisture and grain size, so check them against a truck count on your own site.

Average volume factors from 1 bank m³ (TM 3-34.62, Table 1-1)
Material Loose volume Compacted volume 438 m³ basement, loose
Sand or gravel 1.11 m³ 0.95 m³ 486 m³
Loam (common earth) 1.25 m³ 0.90 m³ 548 m³
Clay 1.43 m³ 0.90 m³ 626 m³
Rock, blasted 1.50 m³ 1.30 m³ 657 m³

So the 438 m³ basement in common earth fills about 548 m³ of tipper space. If each tipper carries 10 m³ loose, that is 55 trips. In clay the same hole needs 63 trips. How much a tipper body actually holds is explained in the guide to tipper capacity, and how swell changes a machine’s hourly output is in the guide to excavator productivity and output.

Backfill and surplus. IS 1200 (Part 27) works out machine backfill as the excavated volume minus the volume of the structure built below ground. In the 2.7 m footing pit above, the PCC bed (0.49 m³), the footing 0.4 m thick (0.90 m³) and a 230 × 450 mm column stub up to ground level (0.10 m³) take 1.48 m³. About 9.45 m³ of the 10.94 m³ goes back, and roughly 1.5 bank m³ (about 1.9 m³ loose) is surplus to cart away. Ram the fill harder than the ground was, and it takes more soil: at the common-earth factor of 0.90, filling 9.45 m³ needs 10.5 bank m³, and the surplus shrinks to under half a cubic metre. Mines use the same bank, loose and compacted figures at a much bigger scale, as the guide to overburden removal shows.

Where do excavation quantities go wrong?

Most disputes between owner and contractor come from four places.

The first is working space. One side measures the pit as dug, the other as drawn. Agree the working space before work starts, and remember the standard pays the smaller of the authorised and the actual figure.

The second is depth. Levels are taken after site clearance, not from the top of the grass or rubbish. On sloping ground a single depth figure is wrong; take levels on a grid or at sections, as clause 4.2 asks.

The third is swell. A truck count is loose volume. Paying for 55 tipper loads as 550 m³ of excavation would overpay the 438 m³ basement by about a quarter.

The fourth is rock. Mixed soil and rock is measured as a whole and the rock separated from the stack with an agreed voids deduction, so agree that percentage in the contract.

When the quantity is settled, it goes into the bill of quantities, set out in the guide to the construction estimate format. Carrying distance and height are paid separately and explained in lead and lift in earthwork.

Before you measure your own site

Take ground levels after clearing and before the first bucket goes in. Write down the working space and the trench allowance your contract allows. Measure each pit or trench as dug, use the smaller of dug and authorised, and convert to cubic feet only at the end. If the excavation is large, ask your engineer which formula the contract uses and keep the level book signed by both sides. For a machine to do the work, compare excavator models and specifications and ask the dealer for output on your kind of soil. Where the dig fits into the order of building a house is shown in the guide to house construction stages.

The sources for this guide were read in November 2026: IS 1200 (Part 1):1992 (reaffirmed 2002) clauses 2.3, 2.6, 4.1 to 4.12 and 5.2, with its Amendment 1 of March 2012; IS 1200 (Part 27):1992 clauses 4.2, 4.4.2 and 4.7; and the US Army TM 3-34.62 Earthmoving Operations (June 2012), Table 1-1 and paragraph 1-11. The worked examples are our own arithmetic. No prices are quoted on this page; rates are in the excavation rate guide linked above. More quantity and cost guides are in the construction cost guides. The final measurement on any contract follows the terms you sign.

Prices, specifications and features are indicative, vary by variant, location and date, and should always be confirmed with the official OEM or authorised dealer before any purchase decision. DesiMachines is not liable for decisions taken on the basis of information that may have changed after publication.