NHAI is adding three 3-lane road over bridges and seven vehicular underpasses to the six-lane Delhi to Agra highway at ₹707.38 crore, and the Delhi Agra ROB tender closes at 11:00 AM on 16 November 2026.
Ten structures spread over 180 km
The work sits between km 20.500 and km 200.000 of the old NH-2, now NH-44 and NH-19, across Haryana and Uttar Pradesh, on EPC mode. The Regional Office at Delhi is the authority, reference NHAI/Delhi /ROB/VUP/NH-19/2026/e-file no. 247160.
Ten separate structure sites on one of the busiest corridors in the country is a logistics problem as much as a construction one. Each ROB crosses a railway line, which means railway blocks, approved girder launching windows and a safety plan agreed with the zonal railway before a single pier goes up.
A 4,380 day period on the portal
The portal records the period of work as 4,380 days, which is twelve years and far longer than ten structures need. On an EPC package this length normally covers a maintenance tail after construction, so read the contract data sheet to see where construction ends and maintenance begins. It changes how you price plant retention.
This is crane and piling work, not earthmoving. Each site needs a piling rig, a crawler crane big enough to launch girders, and transit mixers arriving on a tight window because pours happen in traffic gaps. Excavators handle approach cutting and drainage.
Underpasses are dug in the median or under the carriageway with traffic running either side, so compact machines earn their keep. Backhoe loaders and small compactors do the backfill behind abutments where a large roller cannot reach. Night work is the norm, which means lighting towers and a crew rostered for it.
Key facts
Tender ID
2026_NHAI_268049_1
Reference no.
NHAI/Delhi /ROB/VUP/NH-19/2026/e-file no. 247160
Issuing authority
National Highways Authority of India, Regional Office Delhi
Location
Six-lane Delhi to Agra section, old NH-2 (new NH-44 and NH-19), km 20.500 to km 200.000, Haryana and Uttar Pradesh
Construction of three 3-lane road over bridges and seven vehicular underpasses on the six-lane Delhi to Agra section of old NH-2, now NH-44 and NH-19, from km 20.500 to km 200.000 in Haryana and Uttar Pradesh.
What is the estimated value?
₹707.38 crore, shown as ₹7,07,38,00,000 on the portal.
Why does the portal show 4,380 days?
That is the period of work recorded on the portal, twelve years, which on a package of this type usually includes a maintenance period after construction. Confirm the split in the contract data sheet.
When do bids close?
11:00 AM on 16 November 2026, with opening at 11:30 AM on 17 November 2026. EMD is ₹7,07,00,000.
Tender details are summarised for convenience and may change. Always verify the latest dates, terms and documents on the official tendering portal before bidding. DesiMachines is not responsible for changes made by the issuing authority.
Bidding with your own machines?Tenders often ask for machine papers such as the RC, insurance and invoice. Keep them in one private place on My Machine and get a reminder before insurance or service falls due. Free.
Desi Machines is a platform where you can see and compare construction equipment. It showcases images, brochures, features, technical specifications, brand details & dealer information. All these are taken from respective brand websites, brochures, and other public resources. We do not claim ownership of these materials and strive to ensure their accuracy. However, the disparity may happen and we advise users to verify directly with respective brands and dealers. Desi Machines is not liable for any inaccuracies or reliance on the information provided. Use of this website is at your own discretion.